Home Blog Hybrid_Solar_Inverter_Installation_Guide

Hybrid_Solar_Inverter_Installation_Guide

Sonec
·06/21 11:03
Blog

1. Pre-Installation Preparation

A. Site Selection

  • Choose a well-ventilated, dry location (wall/mounting bracket) with ≥30cm clearance for heat dissipation.

  • Avoid high-temperature, humid, or dusty environments.

B. Tools & Materials

  • Prepare screwdrivers, insulated gloves, multimeter, and cables/breakers matching inverter specs (e.g., 60A DC breaker).

C. System Compatibility

  • Verify PV input range (e.g., 30V-180V), battery voltage (24V/48V), and power rating (e.g., 3000W).

2. Mounting & Hardware Setup

  • Secure inverter to wall/rack using anti-vibration brackets.

  • Install DC disconnect switch and AC distribution box nearby.

3. Electrical Wiring

A. PV Array Connection

  • Connect series/parallel PV strings to PV+/- terminals via flame-retardant conduit.

B. Battery Bank

  • Wire batteries to match nominal voltage (e.g., 24V), attach to Battery terminals with crimped lugs.

C. Grid/Load

  • AC output to load panel (L/N wires); grid-tied models require phase sequence verification.

D. Grounding

  • Connect grounding terminal to earth rod (≥6mm² cable).

4. Commissioning

  • Power sequence: Battery → PV → AC output; check LED indicators.

  • Test voltage stability (220V±5%) and MPPT tracking via monitoring interface.

  • Simulate grid failure to verify backup mode.

5. Safety Protocols

  • De-energize all sources (PV/battery/grid) before wiring.

  • Certified inspection required for insulation resistance/leakage tests.

  • Grid compliance: Obtain utility approval for hybrid systems.